![]() |
||
North Bennington HomeWe had volunteers to the site for the first time on May 16, and we finished the home on the Wednesday before Thanksgiving. We posted photos of the build on this web page from start to finish. We also put some of the photos on Shutterfly. These photos are full size - contain all the pixels and can produce good quality prints. To view those photos individually or in a slide show go to Shutterfly. You can also order prints directly from Shutterfly.
Photo - left - master bedroom.
Patrick and Jen with Jon Cohen who represented them at the closing. This photo was taken right after they had signed all the documents and finally owned their own home!
November 15, 2009 - The Siegrist family at the dedication.
Days 51, 52, 53 and 54- November 4, 7, 11 and 14 We are in the final push to complete the house. Many things, some large (laying the floor in all the rooms) and some small (applying touch up paint), and lots in between Days 47, 48, 49 and 50 - October 21, 24, 28 and 31 Days 45 and 46 - Wednesday and Saturday, October 14 and 16 Great progress was made with the painting. We installed many door jambs and trim around the windows. On Satuday, Thomas Hand and Jim Hand from Hand Energy Services put in 15 inches of cellulose - bringing the attic to an R50 value. More work was done on the door jams and landscaping for planting grass seed. Subsequently, Thomas Hand completed a Blower Door Test to test the air flow. If there is too much air leakage, a house is harder to heat or cool. If there is not enough, the home is too tight and it requires a whole house fan. This house is well sealed and needed a fan. The blower test revealed that this house had a
730 cfm @50. Jamie Hand indicated that this is a very good result. He wrote, "A normal (i.e. fiberglass insulated, standard air sealing) house that
size would probably measure 1200-3000 CFM50. We often measure older
farm houses at up to 10,000 CFM50. So this is very good, probably due
to both the type of insulation, the careful air sealing, but also that
fact that it is a fairly small, simple design." To read more about a Blower Door test, what they mean, and how they might help you to assess your home, go to Blower Door Test. Above - left - Sid Staunton - has done a great job with the joint compound. It is hard to see the joints. Days 43 and 44 - Wednesday and Saturday, October 7 and 9
Days 41 and 42 - Wednesday and Saturday, September 30 and October 2 Led by Dean Hansen and David Quesnel, we primed the ceilings and around the doors and windows. Sid did a great job with the joint compound. and you can't see the joints. He plans to have the third coat on the walls and sanded by Wednesday. We will finish the door jambs and will start painting the rooms on Wednesday.
On Wednesday, September 30, a group from the Equinox Village of Manchester came to tour the home. They met Patrick Siegrist and were shown around the home by Patrick and Nancy Cilo. They are standing in the living room.
Days 39 and 40 - Wednesday and Saturday - September 23 and 26 On Wednesday, we finished the sheetrock. John fixed the soffit on the south side of the house. Sid has finishedt the second coat of joint compound on the sheetrock, and he anticipates being done in time for us to start painting on Wednesday, September 30. On Saturday, we focused mostly on moving the shed. It was quite a feat - using levers, planks, pipes, and some muscle, five of us moved the shed about 25 feet.
Karen and Jim Lee of Solar Pro, worked more on the system. They are shown with Patrick Siegrist. They explained how it will work - saving Patrick and his family a lot of money. The blue tank stores the hot water - it connects to an overflow tank. In the winter months (November - March, they need to employ a back-up system to supplement the heat from the sun. The estimate is that after four years the cost of the system will be saved.
Finishing the sheetrock up and downstairs was the only game in town! Solar Pro installed the solar system and panels. This is a first for us, but we calculate that it will pay for itself in four years - and then the annual savings for the Siegrist family will be significant. On Saturday, our regulars were joined by a group from the Bromley Brook School. Day 36 - Saturday - September 12 A group from the Second Congregational Church of Bennington helped. They worked on the sheet rock - dug along the side of the house to make it easier for the stucco, and applied varnish to the trim boards. It was a very productive day. Day 35 - Wednesday - September 9 We worked on sheet rock and the deck. John finished the siding on the north side of the home. More work was accomplished on the plumbing.
Day 34 - Saturday - September 5
Led by Cliff, Amelia, Preston, Brant, Kathy, Dick, Joe, and Josh worked on the sheet rock. We still have a lot to do next Wednesday. Photo - Left - Cliff and Amelia.
Day 32 - Saturday - August 29 Day 31 - Wednesday - August 26
Day 30 - Saturday - August 22
Day 29 - Wednesday - August 19
Day 28 - Saturday - August 15 Day 27 - Wednesday - August 12 Nikki Gates took the longest distance prize - making her annual trek from Seattle to Vermont and spent a day helping us! Our volunteers were delighted to have Becca, Taylor and Mariah Siegrist vist. Hannah and Brandt finished the siding on the back, others worked on the siding on the other three sides, and we started with the sheetrock on the living room ceiling. Day 26 - Saturday - August 8
Day 25 - Wednesday - August 5 We worked mostly on the siding.
Day 24 - Saturday - August 1 A group from Bromley Brook came to help. We worked mostly on siding.
Day 23 - Wednesday - July 29 We finished the roof, continued work on the siding, prepared for the soffit on the back of the home, poured concrete for the deck posts, and made the forms for the concrete slab for the front door. It managed to get all this done before the rain came.
Preston - Work around the windows requires lots of patience.
We worked on the siding, patched the insulation where we had removed the scaffolding, dug the holes for the deck, blocked the interior walls. and Andy and Paul of Stevens Roofing and Jamie Hand worked on the roofing. A lot was accomplished!
Day 20 - Wednesday - July 15 - A class from the Career Development Center, led by their teacher, Jim Gilbert, helped with the starter strip for the siding. Getting it started correctly, will mean that everything will look just right when done. An 1/8th of an inch off will result in a sloppy job. Jim did a great job showing everyone how to do it correctly. Noble, Carl, and Fred focused on getting the shingles started for the roof. Hannah and Zack helped remove the scaffolding. Hazel did a great job cleaning the basement and brought very tasty muffins for our break. Home Depot brought a great lunch. Day 19 - Saturday - July 12 The siding was started. Photos will be posted later next week. Day 18 - Wednesday - July 8
Day 17 - Saturday - July 4 Day 16 - Wednesday - July 1 Day 15 - Saturday, June 27 A group from the Bromley Brook School came to help. They focused on nailing around the windows to make them more secure. They also fixed some the grading around the home where the rain had created lots of mud. They cleaned and organized the first floor.
Day 14 - Wednesday, June 24 Project Manager, Cliff Beebe and Site Supervisor, David Quesnel worked together the entire day to take stock of our progress and to make plans for the next several weeks. We checked all the windows to make sure they were level. We cut the extensions for the upstairs windows and got all but two in place. We inserted strapping on the celing - organized the building materials, reorganized the trailer, and built most of the interior walls for the basement. It was a good day of work.
Days 12 and 13 - June 19 and 20 Day 11 - June 17 - Global Village Team - Day 3 The team was joined by many Vermonters - as Wednesday is our normal build day. We almost had too much help - but everyone found something to do and by the end of the day, a lot had been accomplished. The interior walls were laid out and put up. The blue board was finished - and we filled most of the cracks and taped the seams until we ran out of tape. The wood trim was cut and installed on the roof. Larry and David worked on the front entrance. We finished the strapping for the ceiling and filled the hole next to the entrance for the electric.
Day 10 - June 16 - Global Village Team - day 2 The team was joined by Lou Midura Builders. They put the sheathing and the felt on the roof. The Global Village Team finished the strapping around the windows, put up more blue board up to the scaffolding, installed most of the strapping on the ceiling, and enjoyed a very productive day. The Second Congregational Church provided a great lunch!
Lou Midura of Midura Builders, and his crew of Justin and Rick Keyes and Rick Dailey did a tremendous job on a steep roof. They contributed their time and talent - a much appreciated gift! This is the fourth year in a row they have helped us in this way!
Day 9 - June 15 - Global Village Team - their first day! We are fond of saying that "teamwork makes the dream work!" and our Global Village Team brought this statement to life throughout the day! The day ended early with an aggressive thunderstorm, giving proof to the statement - if you don't like Vermont weather, just wait five mintues! It went from absolutely beautiful to very nasty in a very short time! Day 8 - June 13 A group from Citizens Bank joined us. A small crew finished putting up all the trusses. We also cut the blueboard away from the window edges. It was a beautiful spring day and a lot was accomplished. At the end of the day Harry Haldt, manager of the West Pawlet Branch of the Citizens Bank, surprised us all by presenting us with a check for $2,500 to help pay for supplies for the Siegrist home.
Day 7 - June 10 We had about a 1/3rd of the trusses up by the end of the day. We welcomed volunteers from the North Bennington branch of the Merchants Bank and the store manager of the Bennington Home Depot. We prepared for the the next big push - putting up the roof trusses. To get ready, we finished the exterior sheathing, set up the scaffolding on both sides, and organized our supplies. It was a picture perfect spring day!
Day 5 - June 3 We completed the north and south walls. We started to insulate the exterior walls. In the basement we installed the lolly columns and cut the insulation. A group from the Gap joined with many of our regular crew
Day 4 - May 30 - A group came from the St. Frances Sacred Heart congregation along with many others. We accomplished a lot, including building and putting up the first two walls!
Left - building the walls - and right - the group from the St. Frances Sacred Heart congregation. We worked on the deck for the first floor, and inserted the perimeter drains for radon in the basement.
We got most of the deck done. Right - students and faculty from Bennington College.
Blue Heron Construction - led by Rick. Photo right - David
Project manager, Cliff. Nailing the decking.
Digging and burying the pipe for the radon was definitely a "career move!"
Back to the Top Day 2 - May 20
We finished building the basement wall. Tracy and Kelley. Left - photo of volunteers from Hoisington Real Estate - "We don't just sell homes, we build them." Right - the end of the day - we were ready to put on the first floor. Day 1 - May 16
Habitat family partners - Jen and Patrick at work building their home!
A group of Yale graduates came to help. Patrick and Jen in front of our trailer - with the Habitat logo - painted by Flying Cow Signs.
Glen Sherman poured built the foundation - using concrete from Daileys. The wet weather has slowed things down - but we should be all set to start on the 16th. We are underway.
We are searching for a family partner and expect to begin building in late April or early May 2009.
The home will be built on the wooded part of the land.
Burr and Burton Academy students built a shed that will be used to store building supplies during construction and will then be used by the family for storage. The shed was built as part of the BBA service learning program.
"Building this shed made me feel useful and helpful. I learned a lot about building and had a wonderful time each morning I got to come. Overall, I am glad for every minute that I was down here helping Mr. Hay. It was for something I am proud of doing and would definitely do it again without a doubt." --Dylan Aakjar |
||
| About Us | Getting Involved | Build Updates | Partner Organizations | Calendar of Events | Habitat in the News | Photos | Housing Assistance | FAQ | Contact | ||
| Bennington Area Habitat for Humanity • P.O. Box 524 • Dorset • Vermont • 05251 - 802-367-1000 | ||